Equinix TY13x Data Center

OperationalE3Official company or government statement

エクイニクス TY13x データセンター

LocationChiba Inzai 泉野2丁目101-8(Municipality centroid)
StatusOperational(as of 2023-06-29)
Power capacity36 MW(Planned maximum (incl. future))
Original (Japanese): 第一期8MW、フル稼働時36MWのIT電力供給を計画。TY12xの隣接地
Nearby power infrastructure
Total generating capacity within 30 km: ~3,929.8 MW (5 plants)
Nearest large plant: 千葉火力発電所 (火力) 1440 MW / ~30 km
Source: National Land Numerical Information — Power plants (MLIT, P03-13(2013年度版)), processed. Sums within a radius tend to be larger in dense urban areas; also consider proximity to a single large plant.

Timeline

Important status transitions are shown in English from structured fields. Free-text titles remain in the original Japanese.

  • 2023-06-29 · Operation
    Operation: Unknown → Operational

    Original (Japanese): TY13x データセンター開設

    Original (Japanese): 東京で2ヵ所目のxScaleデータセンター。TY12x隣接地。第一期8MW、フル稼働時36MW計画。

    Operational
地図を読み込み中…

This pin is the municipality representative point, not the exact facility location

Sources (2)

This page does not determine illegality or impropriety. If you find an error, request a correction.