Mitsui Fudosan Hino DC Project

Pre-consultationE3Official company or government statement

日野DC計画(三井不動産・日野自動車工場跡地)

LocationTokyo Hino(Municipality centroid)
StatusPre-consultation(as of 2026-07-09)
Operators三井不動産(Developer)
Nearby power infrastructure
Total generating capacity within 30 km: ~73.3 MW (3 plants)
Nearest large plant: 品川火力発電所 (火力) 1140 MW / ~33 km
Source: National Land Numerical Information — Power plants (MLIT, P03-13(2013年度版)), processed. Sums within a radius tend to be larger in dense urban areas; also consider proximity to a single large plant.

Timeline

Important status transitions are shown in English from structured fields. Free-text titles remain in the original Japanese.

  • 2026-07-09 · Correction
    Correction: Pre-consultation

    Original (Japanese): 計画変更: 建物高さ72m→63.5m、延床面積を約2.36万平方メートル縮小

    Original (Japanese): 三井不動産が日野市審議会に計画変更を提示。近隣住民向け説明会(6月12日・14日)で高さ縮小を示していた。排熱の影響は「解析中」として数値は示されていない。

    Pre-consultation
  • 2025-02-12 · Other
    Other: Unknown → Pre-consultation

    Original (Japanese): 住民説明会を経て建物高さを修正(協議継続中)

    Original (Japanese): 2024-07-11に三井不動産が計画公表。日野自動車工場跡地に3棟・総延床面積16万2360m2規模。地域住民の反対を受け高さを80m→72m→63.5mへ段階的に縮小。2026年時点でも近隣住民向け説明会が継続しており事前協議段階と判断。

    Pre-consultation
  • 2025-02-12 · Other
    Other: Unknown → Pre-consultation

    Original (Japanese): 住民説明会を経て建物高さを修正(協議継続中)

    Original (Japanese): 2024-07-11に三井不動産が計画公表。日野自動車工場跡地に3棟・総延床面積16万2360m2規模。地域住民の反対を受け高さを80m→72m→63.5mへ段階的に縮小。2026年時点でも近隣住民向け説明会が継続しており事前協議段階と判断。

    Pre-consultation
地図を読み込み中…

This pin is the municipality representative point, not the exact facility location

Sources (3)

This page does not determine illegality or impropriety. If you find an error, request a correction.