NTT DATA Tokyo TKY12 (Inzai/Shiroi Campus)

AnnouncedE3Official company or government statement

NTTデータ 東京第12(TKY12)データセンター(印西・白井キャンパス)

LocationChiba Shiroi(Municipality centroid)
StatusAnnounced
OperatorsNTT DATA Group Corporation(Developer)
Power capacity250 MW(Planned maximum (incl. future))
Original (Japanese): 約250MW規模のキャンパス開発(事業者発表)。第一期棟は2030年以降提供開始予定
Nearby power infrastructure
Total generating capacity within 30 km: ~7,945.8 MW (13 plants)
Nearest large plant: 千葉火力発電所 (火力) 1440 MW / ~25.6 km
Source: National Land Numerical Information — Power plants (MLIT, P03-13(2013年度版)), processed. Sums within a radius tend to be larger in dense urban areas; also consider proximity to a single large plant.
Water resources & flood exposureOpen the water utility and flood layers

Timeline

Important status transitions are shown in English from structured fields. Free-text titles remain in the original Japanese.

  • 2026-04-17 · Announcement
    Announcement: Announced

    Original (Japanese): 約250MWのデータセンターキャンパス開発を始動と発表

    Original (Japanese): 第一期棟は2030年以降のサービス開始を目指す。

    Announced
  • Date unknown · Announcement
    Announcement: Announced

    Original (Japanese): 第一期棟(印西ファイブ特定目的会社)延床約3万平方メートル、2026年1月着工目指す

    Original (Japanese): 設計はNTTファシリティーズ。250MWキャンパス計画の第一期棟に相当すると推定される案件。建設通信新聞報道(着工予定時期は「1月」とのみ判明、年次は記事内で未確定のため保留)。

    Announced
Loading map…

This pin is the municipality representative point, not the exact facility location

Sources (2)

This page does not determine illegality or impropriety. If you find an error, request a correction.