Hokkaido Tomakomai AI Data Center
Under constructionE3Official company or government statement北海道苫小牧AIデータセンター
| Location | Hokkaido Tomakomai(Municipality centroid) |
|---|---|
| Status | Under construction(as of 2025-04-15) |
| Operators | ソフトバンク(Developer)IDCフロンティア(Operator) |
| Power capacity | 300 MW(Planned maximum (incl. future)) Original (Japanese): 将来的に受電容量300MW超・敷地約70万m²まで拡大見込み(報道・事業者発表) |
| Nearby power infrastructure | Total generating capacity within 30 km: ~2,165 MW (6 plants) Nearest large plant: 苫東厚真火力発電所 (火力) 600 MW / ~16.6 km Source: National Land Numerical Information — Power plants (MLIT, P03-13(2013年度版)), processed. Sums within a radius tend to be larger in dense urban areas; also consider proximity to a single large plant. |
Timeline
Important status transitions are shown in English from structured fields. Free-text titles remain in the original Japanese.
- 2025-04-15 · Construction startConstruction start: Under construction
Original (Japanese): 起工式を開催
Original (Japanese): 再エネ100%を掲げる日本最大級のAIデータセンターの起工式。2026年度の開業を目指す。
→ Under constructionSources: ソフトバンクニュース
地図を読み込み中…
This pin is the municipality representative point, not the exact facility location
Sources (2)
- 日本最大級「北海道苫小牧AIデータセンター」起工式ソフトバンクニュース · Official statement · Published 2025-04-21 · Retrieved 2026-07-15Supports: Existence, Operator, Status, Power capacity
- 「北海道苫小牧データセンター」起工式を開催しましたIDCフロンティア · Official statement · Published 2025-04-18 · Retrieved 2026-07-15Supports: Existence, Status