STACK Infrastructure TKY01A Data Center

OperationalE3Official company or government statement

STACK Infrastructure TKY01Aデータセンター

LocationChiba Inzai 原1丁目2(Block-level)
StatusOperational(as of 2024-10)
Power capacity18 MW(IT load)
Original (Japanese): TKY01キャンパス2棟のうち1棟目(A棟)。キャンパス全体で36MW(18MW×2棟)。2024年10月竣工
Nearby power infrastructure
Total generating capacity within 30 km: ~7,945.8 MW (13 plants)
Nearest large plant: 千葉火力発電所 (火力) 1440 MW / ~26.9 km
Source: National Land Numerical Information — Power plants (MLIT, P03-13(2013年度版)), processed. Sums within a radius tend to be larger in dense urban areas; also consider proximity to a single large plant.
Site area23,000

Timeline

Important status transitions are shown in English from structured fields. Free-text titles remain in the original Japanese.

  • 2024-10 · Operation
    Operation: Unknown → Operational

    Original (Japanese): TKY01A棟竣工

    Original (Japanese): STACK Infrastructure日本初のデータセンター。TKY01キャンパス2棟のうち1棟目。

    Operational
地図を読み込み中…

Approximate location

Sources (2)

This page does not determine illegality or impropriety. If you find an error, request a correction.