Data centers associated with 株式会社ゲットワークス: status, MW and sources
3 published facilities and projects associated with 株式会社ゲットワークス, with location, status, capacity types, dates and sources. Focused on AI and hyperscale infrastructure; not a census of all data centers.
Registry updated (distinct from content verification): 2026-10-08 10:59:50
Recorded facilities and projects
Kobe Underground Tunnel Data Center Project
Kobe, Hyogo · Announced · E3
20 MW(Planned maximum (incl. future))
Status as of: 2026-10-06
Content verified: 2026-10-08
Companies: Mitsui Fudosan Co., Ltd.株式会社ゲットワークス株式会社熊谷組
Sources: 三井不動産株式会社・株式会社熊谷組・株式会社ゲットワークス
宮城AIデータセンター(東北電力・七ヶ浜)
宮城郡七ヶ浜町, Miyagi · Operational · E3
Capacity not recorded
Status as of: 2026-07-31
Content verified: not recorded
Companies: 東北電力株式会社株式会社ゲットワークス
Sources: クラウド Watch(インプレス)東北電力
鹿児島出水データセンター(ゲットワークス)
出水市, Kagoshima · Operational · E3
Capacity not recorded
Status as of: 2026-08-01
Content verified: not recorded
Companies: 株式会社ゲットワークス